ACACİA MİNİNG
Sepetçi Wastewater Treatment Plant
Turnkey civil, mechanical and electrical works for a 2,450 m³/day wastewater treatment plant at the Sepetçi site in Hanönü, Kastamonu.

Project Details
| Project Name | Sepetçi Wastewater Treatment Plant |
|---|---|
| Company | Acacia Mining |
| Capacity | 2.450 m³/Day |
| Year Built | 2025 |
| Location | Hanönü / Kastamonu |
| Project Status | Completed |
| Scope of Work | Engineering / Mechanical / Electrical / Civil Works |
The 2,450 m³/day Sepetçi Wastewater Treatment Plant built for Acacia Mining in Hanönü/Kastamonu was delivered by our team from engineering through to commissioning.
Considering the high suspended solids and metal load typical of mining operations, physical pre-treatment, chemical treatment and sludge dewatering stages were designed together. Concrete structures, mechanical equipment manufacturing and electrical/automation works were carried out under a single contract.
Companies Involved