NG KÜTAHYA SERAMİK A.Ş.
Industrial Wastewater Treatment Plant

Project Details
| Project Name | Industrial Wastewater Treatment Plant |
|---|---|
| Client Company / Institution | NG Kütahya Seramik A.Ş. |
| Capacity | 1.800 m³/Hour |
| Year Built | 2026 |
| Location | 30 Ağustos OSB / Kütahya |
| Project Status | Completed |
| Scope of Work | Engineering / Mechanical / Electrical & Automation |
The process selection was made by evaluating the wastewater characterization and discharge limits of the facility; the facility was installed on a turnkey basis.
Processes Implemented
Balancing and pre-treatment
Chemical treatment
Biological treatment
Sludge dewatering
Highlights
Stable output values below discharge limits
Savings in chemical consumption with automatic dosing
Commissioning without stopping production